Work begins next week (Nov. 3) on a major road reconstruction project in Fingal.
The work, which will see the rebuilding of stretches of Union Road and Fingal Line at the four corners in the community will support infrastructure upgrades needed to pave the way for future growth.
The work will include watermain replacement, storm sewer and storm outlet construction, sanitary sewer installation, full road reconstruction, sidewalk installation and improvements and landscape features.
The intersection will include turning lanes to support future development.
myFM talked to Southwold Mayor Grant Jones about possible traffic disruption.
Total cost of the project, expected to be completed in June, 2027, is $7.4 million with the province contributing $3,697,500 and the County of Elgin an equal share.
One factor that had to be taken into consideration was the movement of large farm equipment at times through the growing season.
He stressed rebuilding the intersection of Union Road and Fingal Line will not include a traffic roundabout.
Jones added, “This project will not only improve safety and accessibility, but will also unlock development potential that supports new homes, businesses, and families for years to come.
How Construction May Impact Residents:
Traffic: Roads in Fingal will be closed to through traffic at certain times. Local traffic, including business traffic, emergency services, and municipal vehicles will still have access.
Property Access: Driveway access will be maintained as much as possible. However, there will be times when access will be temporarily unavailable. In advance of these instances, you will receive notice and direction as to where to park.
Water Service: Water will remain available, but short service disruptions may occur when connections are made. Some properties may also be placed on temporary service. You will be notified in advance of any changes.
Sanitary and Storm Services: New municipal connections will be installed by the Township of Southwold. Contractors will coordinate directly with property owners as this work takes place.
Vibration: Construction equipment may cause vibrations. Please protect fragile or valuable items inside your home.
Landscaping and Property Items: Please remove decorations, plants, sprinklers, fencing, and other personal items from Township or County property that you wish to keep. Work will take place up to the property line, and the Township and County are not responsible for items left on public property.
Sod: New sod will be maintained and watered by the contractor for 60 days after planting. After this period, maintenance responsibilities revert back to preconstruction conditions.
Garbage and Recycling: Contractors will collect your garbage and recycling on pickup days by moving containers to a location that can be accessed by collection vehicles. Containers will be returned afterward. Please label your containers with your municipal address.
Safety: For your safety, please avoid the construction area and keep a safe distance from vehicles and equipment.
Mail Delivery: Canada Post has been consulted throughout the project design phase. Temporary community mailboxes will be installed, and directions along with access information will be communicated by Canada Post.
Internet / Phone: Should you lose internet or phone service, please contact your service provider. Should the Contractor come in contact with telecommunications lines they will notify the service provider, but additional repairs may be required on private property which may fall under a separate department.
For updates and information regarding the Village of Fingal Reconstruction, visit: https://engageelgin.ca/fingal.
Written by Ian McCallum