The city is undertaking finishing work this week and next which will result in the closure of Talbot Street from Mary Street to Flora Street.
• Work is moving into Stage 3 of the project which will require a new detour to be set up.
• Work will be undertaken to adjust the maintenance holes and valves in the roadway from Mary Street to Ross St. to Prepare for the final layer of asphalt.
• Maintenance holes and valves will be adjusted 5-6th of October.
• Paving will occur on the 10-11th of October.
• Line painting October 12th
• If all goes according to plan Talbot Street should be reopened in the afternoon/evening of the 13th of October
• The outlined schedule is weather pending and may change